Winstone Factory Asbestos Removal

Winstone Factory Asbestos Removal by Elliott Scaffolding
Winstone Factory Asbestos Removal by Elliott Scaffolding

Winstone Factory Asbestos Removal

Elliott Scaffolding delivered this technically challenging project, and New Zealand’s first Layher Keder XL job, at extremely short notice when the Christchurch based plasterboard factory was shut down temporarily after traces of asbestos were found.

Asbestos safely removed

This ambitious project required the asbestos roof (approx. 5000m²) to be safely removed and replaced within a 6 week window. Elliott Scaffolding, together with the support of Layher’s design and logistics team delivered this solution within a week of the closure of the factory.

Extremely impressed

Trevor Elliott commented that “the client was extremely impressed with the responsiveness of Layher and Elliott Scaffolding” who built and installed the Keder XL roof in less than 4 days. The Layher Keder XL roof also effectively withstood the worst of Christchurch’s inclement spring weather.

Thank you to Trevor Elliott for use of these photos.


Asbestos roof removed and replaced within 6 weeks
Asbestos roof removed and replaced within 6 weeks

MORE SCAFFOLDING PROJECTS


Hybrid Roof Cover in Queenstown

Delivering Confidence from the Ground Up in Queenstown Perched on Queenstown’s exclusive Panorama Terrace, this high-end residential renovation required complete protection from the elements for nearly a year. With full re-roofing and exterior cladding upgrades planned, the client needed a reliable, long-term cover that could handle Queenstown’s changeable alpine weather. All-weather protection for an alpine […] Continue reading

Ngāmotu House

Ngāmotu House Redevelopment Located in the heart of New Plymouth, the building formerly known as the Atkinson Building underwent a major transformation and is now known as Ngāmotu House. This central-city redevelopment required a high-performing scaffolding solution that delivered safe, multi-level access, full weather protection, and efficient material handling over the course of a 12-month […] Continue reading