Pelorus Bridge Scaffold
Transit NZ are upgrading bridges around New Zealand with a “seismic retro fit”. This 1956 built bridge is on the Pelorus River at the top of New Zealand’s South Island, about 16km west of Havelock on SH6.
Scaffold challenge
“The scaffold was a challenge, with only a small 2m wide shelf we could build off up to the bridge. We then spanned out, tied to the bridge twice, then dropped the scaffold 8 metres down towards the water line,” said Lyndon Robinson of Scaffold Marlborough.
Long rock anchors
“We have since then dropped it another two metres so that the geologist could do a rock map to decide where to put in about eight 15m long rock anchors. Then we had a flood warning and had to raise the scaffold to 7 metres off the water line until they start work again.”
Thank you to Lyndon Robinson of Scaffold Marlborough for the use of this photo.
-
Contact
Lyndon Robinson
Company
Location
Website
-
Components
Details
Seismic retro fit
Comments
The scaffold was a challenge, with only a small 2m wide shelf we could build off up to the bridge.
Lyndon Robinson, Scaffold Marlborough

MORE SCAFFOLDING PROJECTS
FlexBeam Cantilever Solution at HWR Building
Cost-effective cantilever solution using Layher FlexBeams When Brazier Scaffolding were approached to scaffold Invercargill’s HWR building, it quickly became clear that a practical cantilever solution would be required. Rather than assembling scaffolding from the ground around the entire structure, the team looked for a smarter approach that would reduce labour and material while still delivering […] Continue reading
Rocket Reclad
Efficient scaffold design for central city reclad Rocket Scaffolding were engaged to support a recladding project on a multi-storey commercial building in central Auckland. With public access beneath and retail operations ongoing, the scaffold design needed to enable safe, uninterrupted access while ensuring the structure could be assembled and dismantled efficiently. Smart solutions for footpath […] Continue reading