Wellington District Court

Wellington District Court
Wellington District court by Geeves Scaffolding

Wellington District Court Upgrade.

The Wellington District Court has undergone a $20 million upgrade to create a more modern, safe environment and improve access to justice services. As part of this project, Geeves Scaffolding (Wellington) was awarded the contract to provide safe access for tradespeople and weather protection throughout the four-stage, 14-month construction process.

Enhanced Access and Protection

Tim Geeves of Geeves Scaffolding explained that a key aspect of winning the contract was the innovative rolling roof design. “We used the Layher Mobile Roof System and Layher Allround to create a flexible weather protection system,” Tim said. “The mobile roof allowed us to reposition the entire canopy quickly and conveniently for different project stages with minimal effort.”

Typically, a crane would be required during construction for such a task, but the Geeves team was able to build the mobile roof from a birdcage scaffold over the building. Additionally, a GEDA hoist significantly sped up the build process, ensuring that scaffolders could work both safely and efficiently.

During the preparation and planning phase, the design was crucial for the client, as it needed to be approved by the Ministry of Justice. “The design gave our client a clear understanding of what the scaffold would look like,” Tim concluded.

A special thank you to Geeves Scaffolding (Wellington) for providing these project photos.



MORE SCAFFOLDING PROJECTS


Hybrid Roof Cover in Queenstown

Delivering Confidence from the Ground Up in Queenstown Perched on Queenstown’s exclusive Panorama Terrace, this high-end residential renovation required complete protection from the elements for nearly a year. With full re-roofing and exterior cladding upgrades planned, the client needed a reliable, long-term cover that could handle Queenstown’s changeable alpine weather. All-weather protection for an alpine […] Continue reading

Ngāmotu House

Ngāmotu House Redevelopment Located in the heart of New Plymouth, the building formerly known as the Atkinson Building underwent a major transformation and is now known as Ngāmotu House. This central-city redevelopment required a high-performing scaffolding solution that delivered safe, multi-level access, full weather protection, and efficient material handling over the course of a 12-month […] Continue reading