Falsework Rotokawa Power Station
Constructing the concrete pedestal to house the main turbine for this new geothermal power station required propping up to 14m in height to support a total weight of 750t.
Single pour
650t was wet concrete, including seven beams up to 2m deep deposited in a single pour over twelve hours. Hugh Laity of Power Scaffold and Access reported that the contractors, Hawkins/Sumitomo JV, were impressed by the 2.5m wide cantilevered working platforms and they “just loved” the stair access.
Thank you to Hugh and Jono Laity of Power Scaffold and Access Ltd for the use of these photos.
-
Contact
Hugh Laity
Company
Location
Website
-
Components
Layher Allround Scaffolding, Temporary Stair Solutions
Details
geothermal power station required propping up to 14m in height to support a total weight of 750t
Comments
contractors were impressed by the 2.5m wide cantilevered working platforms and they “just loved” the stair access
Hugh Laity


MORE SCAFFOLDING PROJECTS
Pipe Bridge Refurbishment
Keeping Dairy Moving Acomplex three-year refurbishment was undertaken to upgrade this 360-metre long pipe bridge in the North Island. With the plant processing up to 14 million litres of milk a day, it was critical that work progressed without interrupting daily operations. Precision Scaffolding for an Operational Industrial Environment DIALOG Fitzroy was engaged to deliver the […] Continue reading
Wallingford Bridge
Wallingford Bridge Strengthening. Located in Hawkes Bay, the Wallingford Bridge project required smart, efficient scaffolding solutions to support essential strengthening and guardrail installation. Rocket Scaffolding, working with Layher systems, provided the access needed for contractors to safely complete their work under complex conditions. Safe, Practical Solutions for a Time-Sensitive Upgrade Todd Price of Rocket Scaffolding […] Continue reading