HomeScaffold Projects Double Car Dumper Shutdown
Double Car Dumper Shutdown
Linkforce Engineering were engaged to undertake a double car dumper shutdown, this encompassed all rolling rails to be replaced along with trunion sets and spill faces.

Due to the car dumper needing to be rotated, Layher Allround was an obvious choice as it could be craned in and out reducing time on erection and dismantle and also allowed minimal work at heights and 50% less labour then previous shutdowns.

15 tonne of Layher Allround was used and was transformed into over 60 scaffolds. It took 12 men, 6 days and 6 nights over a 10 day period to erect and dismantle the 60 scaffolds.

Thank you to Liam McGeever from Linkforce Engineering for the use of these photos.

Linkforce Engineering website: www.linkforce.com.au

Bookmark and Share

Download PDF


pdficon Double Car Dumper Shutdown (2.3 MB)


Links to Layher products


Engineered components from Layher Scaffolding

Buy Layher scaffolding

Purchase these and more genuine Layher scaffolding products by contacting your local Layher representative









 
RSS feed - Layher ScaffoldingYouTube - Layher ScaffoldingTwitter - Layher ScaffoldingFacebook - Layher ScaffoldingLayher Scaffolding