Lothway TBS needed to scaffold up the 45º incline of these water pipes over the Parramatta River at Rydalmere for Sydney Water. Access was required along the pipe to replace the old collars and then to encapsulate for painting.
Jason from Pipeline Rigging, who was doing the labour on this job, said that, "all up, this scaffold took two days to build - it would have taken over a week with the tube and clip we were looking at using."
Thanks to Lothway TBS for the use of this photo.